Re: Schedule for the EVM Mark 1

From: Arthur Keller <arthur_at_kellers_dot_org>
Date: Tue May 18 2004 - 01:40:55 CDT

At 4:43 PM -0500 5/17/04, Douglas W. Jones wrote:
>On May 17, 2004, at 12:47 PM, Arthur Keller wrote:
>
>>Spring 2005 software completed
>>Summer 2005 certified
>
>Utterly unrealistic. The certification process takes much longer
>than this. The problem is, there's a backlog, and there are rumors
>that the queue is serviced on a pay-for-priority basis, so if you
>don't pay the squeeze, the delay for certification might be extreme.
>It's not even clear that pay-for-priority certification is illegal,
>since you're not paying them for a particular judgement.

OK, how long should we leave for software certification? And how
much of the system needs to be certified? Thanks.

Best regards,
Arthur

-- 
-------------------------------------------------------------------------------
Arthur M. Keller, Ph.D., 3881 Corina Way, Palo Alto, CA  94303-4507
tel +1(650)424-0202, fax +1(650)424-0424
==================================================================
= The content of this message, with the exception of any external 