On May 17, 2004, at 12:47 PM, Arthur Keller wrote:

> Spring 2005 software completed
> Summer 2005 certified

Utterly unrealistic. The certification process takes much longer
than this. The problem is, there's a backlog, and there are rumors
that the queue is serviced on a pay-for-priority basis, so if you
don't pay the squeeze, the delay for certification might be extreme.
It's not even clear that pay-for-priority certification is illegal,
since you're not paying them for a particular judgement.